每期慧翔天地小编都会附上5~10道PMP®综合测试题,以帮助大家达到练习的效果,本期PMP试题答案会附加在下一期的结尾。大家如果想了解2025年PMP®考试报考流程、PMP®报考时间、PMP®报考条件、PMP®报考费用、PMP®报考资格测评等等均可访问站内进行了解。
PMP备考刷题交流群:667625965(点击一键加群)
6、你正在为一个为当地电力公司安装智能无线电表的多阶段项目开发基准。第一阶段将准备基础设施,第二阶段将安装仪表,第三阶段将上传软件。然而,由于反无线技术组织的反对,尚不清楚该项目是否会在整个规划区域全部完工。在项目过早关闭的情况下,为了增加交付价值的机会,你的最佳行动方案是什么?
A:要求当地政府为项目团队成员提供必要的安全措施,以保护他们免受与反无线技术团体的潜在对抗
B:获得发起人的批准,向那些同意额外工作以尽快完成工作的人提供奖金,即使这涉及到在夜晚和周末轮班工作
C:建议将项目从多阶段切换到一阶段方法,并完成基础设施准备、仪表安装和软件上传,迭代一次一个邻域
D:建议项目终止,因为在方案中描述的情况下,无法按时、按时完成项目、范围和预算,并为客户提供任何价值
You are developing baselines for a multi-phase project to install smart wireless meters for a local electric utility company.The first phase will prepare infrastructure,second will install the meters,and third will upload the software.However,due to the opposition of anti-wireless-technology groups,it's unclear if the project will be completed all across the planned region.What is your best course of action to increase the chances of delivering value in case the project closes prematurely?
A.Request that the local government provide the necessary security measures for the project team members to protect them from the potential confrontation with the anti-wireless-technology groups
B.Get approval from the sponsor to offer bonuses to those who agree to work extra time to complete the work as fast as possible even if this involves working in shifts during nights and weekends
C.Suggest switching the project from a multi-phase to one-phase approach and complete infrastructure preparation,meters'installation,and software upload in short iterations one neighborhood at a time
D.Recommend project termination since under the circumstances described in the scenario there is no way to complete the project on time,scope and budget,and deliver any value to the customer
7、Agile is a well adopted methodology now.There are many ad vantages Agile provide to organizations who are well versed with Agile in their projects.Which of the below is not one of the benefits of Agile?
敏捷现在是一项反响良好的方法。敏捷为在项目中精通敏捷法的组织提供了很多优势。以下哪项不是敏捷的优势?
A、It shorten the time to market它缩短了进入市场的时间
B、Provides business value early and regularly及时且定期提供商业价值
C、It encourages silos and individuals concentrate on their our work
它鼓励个人存储信息和将个人集中精力在自己的工作上口
D、Better customer satisfaction by customer being part of the team
因为客户成了团队的一部分,所以客户满意度更高
8、项目经理正在领导一个新产品开发项目,该项目目前执行顺利,在项目中途,客户希望通过减少功能来简化产品,同时保持项目的进度和成本。项目经理应该怎么做?
A、向变更控制委员会(CCB)提交一份变更请求
B、请求项目发起人批准
C、更新变更管理计划。
D、减少产品功能
9、Team members on a project are performing,but fail to meet deadlines due to work overload.Five more resources are added to the team to ease the situation.What development stag e does this describe?
项目的团队成员正在执行工作,但由于工作超负荷而无法满足截止日期.为了缓解这种情况,团队又增加了五个资源。这描述的是哪个团队建设阶段?
A、Performing成熟阶段
B、Norming规范阶段
C、Storming震荡阶段
D、Forming形成阶段
10、A project manager receives a report from the team that new widgets being created fail to meet the requirements of the project specifications.The report lists multiple causes for the n on-conformance under several problem areas,which could lead to the problem's root cause.What type of data representation tool or technique did the team use
项目经理从团队收到—份报告,称正在创建的新组件未能符合项目规范的要求.这份报告列出了各个问题领域中不合格的多种原因.而这可能识别出问题的根本原因。团队使用的是哪一种数据表示工具或技术类型?
A、Flowchart.流程图。
B、Histogram.直方图。
C、Affinity diagram.亲和图。
D、Ishikawa diagram.石川图。
(250807)答案
1、B
2、C
3、C
4、D
5、A